Industry: Renewable Energy

Project Type: Specialized Transportation

What We Did: Transport of a 60 metric ton steam generator from Fraser Surrey Docks, Surrey, BC to a new biomass energy project near Fort St. James, BC, as well as multiple accessorial loads. Due to the timing of the ship0ment, the load arrived during the seasonal load restriction period in British Columbia, meaning we had to deal with significantly reduced axle weights for transport. Once loaded, we only had 900 kgs. to spare. Our scope also included placement of the load on site.

What We Used: Ultra light 13-axle, 120 ton hydraulic all terrain, 240 hydraulic all terrain.

The Details:
Generator weighed 60 metric ton. Its dimensions were “25’ long x 14’ wide x 13’6” high